A40 bus lanes and junctions from Eynsham park and ride to Cassington start in spring 2027, Cabinet agreed. Duke's Cut is paused after a £14.2m cost rise.
Construction of the A40 bus lanes and junction upgrades between Eynsham park and ride and Cassington is set to start in early spring 2027. Oxfordshire County Council’s Cabinet agreed on Tuesday 20 October to take that stretch into construction. Work is expected to last at least two years.
The last part of the scheme, at Duke’s Cut on the approach to north Oxford, has been paused. So has the work to strengthen the Duke’s Cut bridge. The county’s report to Cabinet says the whole programme is now forecast to cost £14.2 million more than its approved budget.
This is the road almost every Witney commuter to Oxford uses. The approved stretch starts at the park and ride about five miles east of the town.
What Cabinet agreed
The council announced the decision in a news release on 20 October. The approved stretch, which the report calls Phase 1A, includes:
- bus priority measures
- junction improvements
- crossings
- better routes for walking, wheeling and cycling
The report says Phase 1A “delivers the majority of the programme’s transport, bus-priority and active-travel benefits”. Balfour Beatty is the contractor.
Cabinet set a budget of £136.6 million for Phase 1A. That is the existing £132.8 million programme allocation plus £3.8 million from the council’s capital reserves. Of the extra money, £1.1 million is project funding and £2.7 million is a contingency held for this project.
The existing allocation is made up of £106.76 million from the Housing Infrastructure Fund, £19.55 million from the Department for Transport, £5 million of maintenance funding and £1.5 million from developers under Section 106 agreements.
What has been paused, and why
Three pieces of work are on hold:
- Phase 1B, about 800 metres of bus priority on the A40 at Duke’s Cut
- Phase 1C, improvements to the shared path between the Cassington and Duke’s Cut bridges
- the Duke’s Cut bridge strengthening works, awarded to M Group, which the council has not yet signed a contract for
The report puts the current estimate for the Duke’s Cut maintenance and improvement work at about £13.2 million. It says the bus lane there depends on the bridge being repaired first, plus utility diversions and approvals from Network Rail.
Officers judged that part of the scheme to carry “materially greater technical, financial and delivery risk”. Pausing it gives time for more structural surveys, cheaper designs and a funding plan. The work would then go ahead as a separate project, and a further Cabinet decision would be needed before any construction contract.
Councillor Liz Leffman, the Cabinet Member for Highways Construction and Repair, said in the release:
“We need to make sure that we fully understand the work required, the costs and the risks before committing further public money to that section of the scheme. Pausing this element does not mean it is being abandoned.”
The report says bus priority at Duke’s Cut remains council policy. The council has committed to “all reasonable endeavours” to bring it forward as soon as practicable.
The bridge
The report says putting off the bridge maintenance presents “a low overall risk” to the structure at its current level of use. The main risk it names is debris from deteriorating concrete falling onto the railway below. It rates that as low likelihood but potentially high impact.
Inspection, monitoring and any urgent repairs now pass to the council’s highway maintenance service, funded from its normal maintenance budget.
Where the extra cost comes from
The programme forecast is now £147 million, against an approved baseline of £132.8 million. That is a rise of 10.7%, before contingencies.
For Phase 1A, the report blames extra design work to meet planning requirements, replacing existing assets, clashes with utilities and higher utility diversion costs. Construction target costs also rose because of risks around drainage, flooding, the road surface and ground conditions.
Senior officers are now carrying out what the report calls “an urgent review” of budget estimates and contingency levels across the council’s major transport schemes.
What still has to happen
The decision depends on Homes England, which provides the Housing Infrastructure Fund money, formally agreeing to drop Duke’s Cut from the scheme. The report says Homes England “have indicated they are content”, but at the time of writing formal consent was awaited.
The council plans to sign a revised funding agreement through October and early November. Only then can it issue Balfour Beatty with a notice to start construction. The Housing Infrastructure Fund money has to be spent by 31 March 2028.
The report says no homes are cut from the scheme, and the pause does not stop any planned housing from going ahead. No public consultation was held on this decision.
What it means for you
- If you drive the A40 to Oxford: expect a long period of roadworks between Eynsham and Cassington from spring 2027, lasting at least two years. No traffic management plan has been published yet. Our roadworks and travel page will carry it when it is.
- If you take the bus: the S1, S2 and other Oxford services should gain bus priority on the Eynsham to Cassington stretch once it is built. Bus priority at Duke’s Cut, on the final approach to north Oxford, is not being built for now.
- If you cycle or walk: the new routes come with Phase 1A. The shared path between the Cassington and Duke’s Cut bridges is part of the paused work.
- The road is not being dualled. As we reported earlier, this scheme is bus priority and active travel, not extra lanes for general traffic.
Sources
- A40 HIF2 Programme, Phase 1 (A, B and C) and Duke’s Cut Maintenance Update, report to Cabinet, 20 October 2026, Oxfordshire County Council, for the budget, the cost breakdown, the paused phases, the bridge risk, the Homes England conditions and the funding deadline.
- Next stage of A40 improvements agreed, Oxfordshire County Council, 20 October 2026, for the decision, the start date, the length of the works and Councillor Leffman’s quotes.
- Cabinet meeting, 20 October 2026, Oxfordshire County Council.
Have your say